Due to the scale and schedule of this project, TiePoint-bkm has been retained to provide on-site QA/ QC, Level 2 (installation verification and testing validation) and L3 (pre-functional) commissioning, prior to handing off the L4 (functional testing) and L5 (integrated systems testing) to another Cx provider. To accomplish this task, TiePoint-bkm has four fulltime personnel on site for a continuous 12-month period.
Electrical Infrastructure: The data center building is powered from four 1,200A 27kV / 13.8kV outdoor Site Distribution Centers serving 2,000A 13.8kV MV distribution SWGR. The MV SWGR in turn supports a total of 80 Critical Power Unit Substations (1,800A at 13.8kV / 416V). The Unit Substations (20 per floor) feed a series of overhead busways serving the IT cabinets. Critical power is backed-up by six 2.75 MW Engine-Generators per floor (24 in total).
Mechanical Infrastructure: The 55 MW data center building is supported from an existing 24,000 ton central Chiller Plant connected to a common 42” header, with dual-path distribution extending overhead throughout the campus. This data center building has a pair of 20” cross mains, supporting a looped network of piping on each floor. Custom overhead fan coil units provide the critical cooling throughout each cold aisle (approximately 80 per floor, 320 units in total).
Project Highlights
Notifications